| |
| June 1 st Click on any image to enlarge photograph |
| On June 1 st we were called for a trailer that was leaking Lead Sulfate. Upon arrival found that the trailer was leaking from the bottom. After safety zones were established and decontamination was set up technicians suited in level “B” PPE with SCBA to make entry into trailer. PPE was selected for both inhalation hazard and corrosive liquid that appeared to be present. Technicians found that liquid was leaking from trailer and that there were visual signs that the bags of powered Lead Sulfate were wet. Decision was made to unload bags and wipe down bags that were covered with residue. |
 |
 |
| When weather maps revealed that rain showers had passed, heavy gauge plastic was installed and bags placed on it. After all bags were removed, cleaned and, inspected for damage, trailer floor was cleaned and neutralized. Trailer was lined with heavy gauge plastic to prevent leaching and bags were then reloaded into trailer. |
 |
 |
| September 20 th Click on any image to enlarge photograph |
| On September 20 th we got a call for a tank of heating oil that had tipped over in a yard due to severe flooding. Upon arrival found that oil had pooled all over the yard. |
 |
 |
| Installed booms and pads to contain spill and advised homeowner that yard needed to be excavated to prevent environmental impact. |
|
 |
| September 21 st Click on any image to enlarge photograph |
|
 |
On September 21 st we got a call for a diesel fuel spill from a tractor trailer that had been involved in an accident and had ruptured both fuel tanks causing a fuel spill on the shoulder of the roadway and down the embankment. The fuel had also drained into a storm water drain that had discharged over the embankment broadening the spill. |
 |
 |
The area that was contaminated with fuel was excavated to Department of Environmental Protection standards. Area close to site off of the Interstate was chosen to stage contaminated soil. A tri-axle dump truck was used during excavation to transport top soil, to replace excavated soil, and to transport contaminated soil to staging area. Contaminated soil was placed on heavy gauge plastic and covered until FC1 paperwork could be completed and disposal approved. When excavation was completed, samples were taken and documented by technicians then sites were backfilled with top soil, seeded, grated, and rolled. After approval for dumping was granted the contaminated soil was loaded onto a tri-axle dump truck and a dump trailer and transported to the landfill for proper disposal.
Recovery of tractor and trailer was performed by Minuteman Towing and Repairs, Inc. |
| September 14 th Click on any image to enlarge photograph |
| On September 14 th we got a call for a tractor trailer loaded with Calcium Chloride Pellets that had rolled over, blocking both lanes of traffic. Upon arrival found that cargo had gone through the roof of the trailer and all over the interstate. Technicians suited in level “B” PPE and proceeded with cargo transfer. |
 |
|
All cargo that was not damaged was stacked onto pallets, shrink wrapped, and loaded onto a replacement trailer. Any unsalvageable cargo was put into fifty-five gallon drums, sealed, and transported to the landfill in a tri-axle dump truck for proper disposal.
Recovery of tractor and trailer was performed by Minuteman Towing and Repairs, Inc. |
 |
 |
|
|
 |